Debris Removal
I have been awarded a job at an old hotel which is 7 stories high and debris removal is going to be a giant pain. Only 2 sides of the building are accessible and on one of the accessible sides there will be a crane and a stagng area for new steel, on the other they will be erecting curtain wall. While this is all goin on i cannot chute off either side of the building. Does anyone have any ideas as how debris can be removed from the job without walking it all the way down 14 flights of stairs or stockpiling? All ideas are welcomed no matter how far fetched they may sound.
Much appreciated - Chris
|