Demolitionforum.com Forums  

Register Now! Demolition Tool Store - Demolition Gallery - Classifieds - Advertising Info - Forum Guidelines

Welcome to Demolition Forum, the only Online Source for Demolition News and Discussion.

You are currently viewing our boards as a guest which gives you limited access. By joining our free community you will have access to reading the latest in Industry News, Read and learn from the experts, Upload your own demolition photos to your photo album, read and learn from the experts, and many other special features.

Registration is fast, simple and absolutely free so please, join our community today!

If you have any problems with the registration process or your account login, please contact us.


Go Back   Demolitionforum.com Forums > DEMOLITION TOPICS > Industry News

Industry News Updated Every Weekday! Read and share the latest in demolition news from around the world. Where you can read industry press releases or add your own.


Why not Register? or Log in to remove these ads
Reply
 
LinkBack Thread Tools Search this Thread Display Modes
  #1 (permalink)  
Old 06-08-2007, 09:10 AM
James's Avatar
Administrator
 
Join Date: Aug 2005
Location: Kent, WA.
Posts: 4,294
Send a message via AIM to James Send a message via MSN to James
Default Lakeview Generating Station June 25th

If all goes well, a series of 53 explosions using 726 pounds of dynamite will cause the remaining portion of the huge powerhouse at Lakeview Generating Station to start folding in on itself in collapse early on June 25.

The remaining structure, about 1,200 feet long, 300 feet wide and 200 feet high, will implode, causing a giant dust cloud that will drift out over Lake Ontario, if weather conditions cooperate, a spokesperson for Murray Demolition said yesterday at an information session for local ratepayers.

“The key is to wait for the right weather conditions,” Kareem El-Khatib told The News at the former coal-fired station, which closed in April 2005.

The ideal conditions would be a northwest wind of at least 20 km/h and pouring rain, El-Khatib said.

The wind is critical to blow the dust out over the lake and away from the residential area to the north. Rain will help reduce dust when the hundreds of thousands of tonnes of equipment and steel hit the ground.

The implosion is designed to have the structure destroyed in sequence, so that the demolished sections pile up on one another. The twisted remains should be about 100 feet deep.

Instead of removing huge pressure vessels suspended from the roof, it was deemed safer to leave them up and have them fall into the pile of refuse that will be created below.
If there's not a strong northwest or north wind, the explosion will not go ahead, even if it means waiting all day or until later in the week.

Because the main force of the dust ball created by the demolition will go out over the lake, the exclusion zone for boats has been extended from one to two kilometres. There will be a 500-metre ban on movement around the plant for people and cars. No traffic will be permitted on Lakefront Promenade for an hour before the scheduled 7:30 a.m. blast.

The debris created by demolition of the iconic “Four Sisters," the nearly 500-ft. tall stacks at the plant knocked down one year ago, has been piled up around the site to create a kind of berm to reduce the impact on surrounding homes.

Most of the equipment in the powerhouse has already been removed and disassembled. The coal pile, which along with the stacks was the identifying symbol of the plant for 43 years, has also been removed. That area has been cleared to the ground and re-seeded.

Ontario Power Generation (OPG) has donated several artifacts from the plant to the City of Mississauga, which included the plant in its cultural landscape inventory because of its historical significance. It's hoped the artifacts will be displayed in local parks near the site.

Richard Schwass, OPG senior communications advisor, said about 90 per cent of the material from the powerhouse will either be reused or sold for recycling, including much of the high-quality steel used to construct the plant in the 1950s.
__________________
Still just visiting? Come say Hello!
We have some open advertising spots available
Reply With Quote
Sponsored Links

Why not Register? or Log in to remove these ads
  #2 (permalink)  
Old 06-23-2007, 03:08 PM
NukeWorker's Avatar
Senior Member
 
Join Date: Jul 2006
Posts: 847
Default

That's a big building (7.2 Million cf). It should be something to see.
Reply With Quote
  #3 (permalink)  
Old 06-24-2007, 05:48 PM
Member
 
Join Date: Mar 2007
Posts: 6
Default

I went out to the area to scout sites outside the exclusion zone for photographing the shot. Signs were posted that the shot has been postponed. It will go the first day that they have winds from the North or rain, forecast doesn't look good for Tuesday either, Wednesday may happen in the rain.
Reply With Quote
  #4 (permalink)  
Old 06-25-2007, 08:13 AM
NukeWorker's Avatar
Senior Member
 
Join Date: Jul 2006
Posts: 847
Default

What are they afraid of? All the hazardous materials have been removed.
Reply With Quote
  #5 (permalink)  
Old 06-25-2007, 09:48 AM
James's Avatar
Administrator
 
Join Date: Aug 2005
Location: Kent, WA.
Posts: 4,294
Send a message via AIM to James Send a message via MSN to James
Default

Lakeview's official word:

The demolition scheduled for Monday, June 25, 2007 has been postponed. Wind conditions are not right.

The demolition company will re-evaluate conditions on Monday and OPG will
issue an update as soon as we have further information.
__________________
Still just visiting? Come say Hello!
We have some open advertising spots available
Reply With Quote
  #6 (permalink)  
Old 06-26-2007, 06:50 AM
Member
 
Join Date: Mar 2007
Posts: 6
Default

The site is only just over a kilometer from a major highway, although they are pushing the as "respect for their neighbors" I suspect the real reason is concern that the dust cloud would cause visibility problems on the highway during morning rush hour.
Reply With Quote
  #7 (permalink)  
Old 06-27-2007, 09:43 AM
James's Avatar
Administrator
 
Join Date: Aug 2005
Location: Kent, WA.
Posts: 4,294
Send a message via AIM to James Send a message via MSN to James
Default

The scheduled demolition of Mississauga's Lakeview Generating Station, originally scheduled for today, has been delayed till Thursday morning.

The demolition company -- Murray Demolition of Toronto -- did not feel the conditions were right, but did not specify reasons for the delay.
__________________
Still just visiting? Come say Hello!
We have some open advertising spots available

Last edited by James; 06-27-2007 at 09:53 AM.
Reply With Quote
  #8 (permalink)  
Old 06-27-2007, 12:55 PM
Member
 
Join Date: Mar 2007
Posts: 6
Default

I was out at the site, it was dead still, no wind at all until about 9:30ish then when the wind did start to pick up it was blowing in off the lake, wrong direction. I think they were hoping for rain which did not materialize.
Reply With Quote
  #9 (permalink)  
Old 06-27-2007, 01:57 PM
NukeWorker's Avatar
Senior Member
 
Join Date: Jul 2006
Posts: 847
Default

The best angle to photograph the implosion is from the corner of Hydro and Rangeview.

The Discovery Channel is doing a whole show on the implosion. They are also going to have a webcast.
Reply With Quote
  #10 (permalink)  
Old 06-27-2007, 02:35 PM
Member
 
Join Date: Mar 2007
Posts: 6
Default

I was there for a while this AM, from outside the exclusion perimeter at Hydro and Rangeview you can't really see all of the site due to trees, buildings etc in the foreground.

There is an area with great sight lines well inside the exclusion fence south of Rangeview on Hydro, where Discovery and others are shooting from but that is available to accredited media only, CTV had their satellite truck there this morning.

I drove or walked almost all of the perimeter and the location where you can best catch the whole North face of the powerhouse is on the west side where the perimeter crosses Lakeshore Promenade.

I'd love to find a way to be allowed into the media area...
Reply With Quote
Sponsored Links

Why not Register? or Log in to remove these ads
Reply


Currently Active Users Viewing This Thread: 1 (0 members and 1 guests)
 
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump


Forum Sponsors



Partners
Dexpan Silent Demo
Diamond Tools SuperCenter
High Reach Demo
Scrap Metal Prices
EnviroBidNet
Heavy Equipment Forums
Lawn Cafe
Phillyblast
Excavator Trader
Home Theater Forum

Advertising Partner


All times are GMT -7. The time now is 06:00 AM.


Powered by vBulletin® Version 3.7.4
Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Optimization by vBSEO 3.2.0
© 2005-2008 DemolitionForum - All Rights Reserved