The whole project seemed to fly under the radar for ethics. The project seemed to just "slip" unde the City of Indianapolis "legal" wire for consultation without bid number. If I remember correctly, it was about $300k. Funny, I bid $90k for the same work and was told the project was "negotiated. Oddly enough. The contractor tolr me last month he would rather have had taken the dome down with a ball instead of the aggravation caused by poor fragmention. Call Curtis Schopp and verify this.