View Single Post
  #3 (permalink)  
Old 03-27-2007, 03:55 PM
NukeWorker's Avatar
NukeWorker NukeWorker is offline
Senior Member
 
Join Date: Jul 2006
Posts: 844
Default

If I remeber correctly, that didn't work too well on the demolition of the Market Square Arena.

The first time they bid the project the low bidder was going to build a giant ramp and walk his excavators to the roof and hammer it down.

Then they rebid it to blast it and that didn't work out very well. The contractor in charge of the debris removal ended up suing because the debris didn't break apart.